Polynomial-time scheduling on three identical machines
Result described by OpenAIResolves the three-processor unit-job scheduling problem of Garey and Johnson: a deterministic polynomial-time algorithm minimizes makespan for nonpreemptive unit-length jobs with arbitrary precedence constraints on three identical parallel machines. For an explicitly given precedence graph, it decides deadline feasibility exactly and constructs a feasible schedule.
No reviewed explanation artifact is available for this family. This empty slot is not evidence that the result is unproven; it means no explanation draft has been prepared and reviewed for this snapshot.
Abstract from the sourceWe give a uniform deterministic polynomial-time algorithm for scheduling unit-length jobs with arbitrary precedence constraints on three identical parallel machines. The algorithm constructs a schedule of minimum makespan and decides exactly whether all jobs can finish by a specified deadline. The proof reorganizes feasible schedules into intervals whose job sets have descriptions of bounded size. A dynamic program searches a family containing polynomially many such descriptions. Global boundary conditions and simplification of inherited information keep the descriptions bounded throughout the decomposition.
Formalization evidence
This manuscript is named in the family’s scope document. Read the scope below for the exact conclusions covered.
BibTeX citation from OpenAI
@misc{OAI:A-polynomial-time-algorithm-for-three-machine-unit-job-scheduling-September-24-2026,
author = {{OpenAI}},
title = {{A Polynomial-Time Algorithm for Three-Machine Unit-Job Scheduling}},
howpublished = {OpenAI Math Release preprint
\href{https://github.com/openai/math/blob/main/preprints/A-polynomial-time-algorithm-for-three-machine-unit-job-scheduling-September-24-2026/paper.pdf}{OAI:A-polynomial-time-algorithm-for-three-machine-unit-job-scheduling-September-24-2026}},
year = {2026}
}
Source snapshot: 1581d4cbdd69. The citation above retains OpenAI’s original wording.
Inspect what was formalized
Lean proof scope
Described by OpenAI · not replayed by Proofweave
Scope statement from the source
The formalization gives a deterministic polynomial-time algorithm for scheduling nonempty collections of unit-length jobs with arbitrary acyclic precedence constraints on three identical parallel machines. It constructs a schedule of minimum makespan and decides exactly whether a valid specified deadline can be met. The algorithm is one fixed finite machine, and its running time is bounded by a polynomial in the binary input length.
These records describe upstream evidence. A platform replay, a review of the theorem’s meaning, and an independent review still need their own evidence.
The proofs share a large library. OpenAI recommends compiling selected portions at a time. Use the pinned environment and inspect the Comparator instructions before attempting a replay.